Project Overview: Constructing concrete abutments for a new pedestrian bridge over 3 Mile Creek and installing the prefabricated bridge. Project also included 300 SY of 6” concrete bike path, landscaping and irrigation system installation. Adjacent road improvements included constructing 420 LF curb and gutter and paving an 8-foot wide shoulder along the east side […]
New Castle Pedestrian Bridges
Project Overview: Project included three prefabricated bridges across the UPRR tracks, I-70 and the Colorado River. Project also includes an eight foot wide pedestrian/bicycle trail connecting the bridges to the Highway 6 corridor and the CR 335 corridor.
Two Rivers Bridge
Project Overview: Two Rivers Bridge spans the Colorado River at its confluence with the Roaring Fork River and provides pedestrian access to Two Rivers Park. At the time of the bid, the City of Glenwood Springs had ordered the bridge for Steadfast Bridge, but the designers had not come up with a solution regarding […]
Snowmass Base Village Bridge #2
Project Overview: This bridge provides pedestrian access as well as fire access to Snowmass Base Village. Scheduling of this project was of utmost importance to the owner due to the fact that vertical construction of Base Village was halted until the fire access bridge was in place. Other challenges faced on this project included; […]
Satank Bridge Rehabilitation
Project Overview: The Satank Bridge, is both the longest span timber truss bridge in the state, and also the last of the timber truss bridges still in use in Colorado. The original Satank Bridge project was awarded to the Pueblo Bridge Company on May 12, 1900. The 2010 Satank Bridge rehabilitation project involved lifting […]
Devereux Road Pedestrian Bridges
Project Overview: The Devereux Pedestrian Bridge project was constructed to get pedestrians safely over Interstate 70. Gould Construction crews constructed 5,532 SF of Keystone MSE retaining walls. Four concrete abutments a top steel piling were constructed to accept a 124 foot bridge in Two Rivers Park and a 206 foot bridge over I-70.
Clifton Pedestrian & Utility Bridge
Project Overview: This project features two primary components, which includes a 390-foot long pedestrian and utility bridge spanning the Colorado River and approximately 4,000 linear feet of 30-inch gravity sewer line. The bridge structure consists of three prefabricated superstructure truss units supported by cast-in-place concrete piers and abutments. Utilities on the bridge include a […]
Almost Paradise Bridge
Project Overview: The Almost Paradise Bridge project involved preserving and rehabilitating the original bridge with steel girders and replacing and reinforcing the concrete center pier and abutments. The bridge goes over the Frying Pan River to a private residence. Western Wood Structures provided the Super Structure and PSI set the bridge after reinforcement. […]
Atkinson Trail
Project Overview: Construct path and install 8400 LF of 10ft wide colored concrete bike path along the Roaring Fork River in Glenwood Springs. Included is four bridge spans, totaling 265 foot built under the 27th street bridge. Two abutments and 3 piers were installed to support the bridge. Two of the piers were […]